Manor Progress 8/1/15

August 1, 2015 by Deena
Comments Off on Manor Progress 8/1/15

The construction project continues to move along. About 75% of the curb and gutter around the facility has been poured and about 90% of the sidewalks are in place. The parking lot and exterior lighting have been installed and we are discussing the landscaping. The excess piles of dirt on the site are being spread and the site continues to look more and more like it will when it’s done. We are busy planning the steps to move residents into the new facility and work out issues for operations.IMG_0191 IMG_0192 IMG_0202 IMG_0207 IMG_0210 IMG_0211 IMG_0213 IMG_0214 IMG_0215 IMG_0216 IMG_0217 IMG_0218

«
»